In this topic, you will learn how to prepare a new discretionary award in G5.
Steps:
Hover over Grant Maintenance on the toolbar at the top of page then click the Prepare menu item to begin the process of preparing an award.
Step 1Enter the appropriate information in the Fiscal Year field.
In this example, enter "2025".
Step 2Enter the appropriate information into the CFDA/Subprogram field.
In this example, enter "84.432B".
Step 3Enter the appropriate information into the Schedule No. field.
In this example, enter "1".
Step 4Click in the Award Type field to display the list of award types.
Step 5Select Discretionary in this example.
Step 6Click in the Action Type field to display the list of action types.
Step 7Select New Competition list item in this example.
Step 8Click the Search button to search for the awards which meet the search criteria.
Step 9The list of awards that match the search criteria will appear. Note that the Funding Status must be Committed to prepare a new discretionary award.
In this example, click the appropriate radio button to select PR/Award No P432B250004.
Step 10Click the Prepare Award button to prepare the award.
Step 11Click the vertical scrollbar to scroll down.
Step 12Click the Verify UEI button to verify UEI information.
Step 13At the top of the UEI Verification section, the information from the Recipient System (RS) is listed. At the bottom is the Grantee Information. The two must match in order for you to verify the UEI information.
Step 14Click the Select option to mark the Recipient System information for UEI GGG777HHH894.
Step 15Click the Select button to select the Recipient UEI you have marked.
Step 16Note that the Recipient UEI information that you selected is now displayed next to the Grantee UEI information at the bottom of the screen.
Step 17After you have reviewed both sets of information, click the Verify button to verify that the UEI information matches for both.
Step 18Note: If the applicant's SAM.gov registration is inactive, a warning message will appear and you will be asked to confirm if you want to continue. To verify the UEI, please select Yes.
If you do continue, the award must be marked as exempt from SAM verification before it can be obligated. For instructions on that process, please see the Set Exempt Award Indicator topic in the Grant Maintenance module.
Step 19In this example, click the Yes button to confirm you want to continue.
Step 20The system displays a message indicating that the UEI has been successfully verified.
Step 21Click the vertical scrollbar to scroll down.
Step 22Click the Continue button to continue to the Contacts tab.
Step 23The Contacts tab displays information for the ED Program Contact, Project Director, and Certifying Representative.
Step 24After confirming the contacts are correct, click the Continue button to continue to the Clauses tab.
Step 25The Clauses tab displays the list of mandatory award clauses which will be applied to the award. The clauses listed may be mandatory for a specific CFDA/Subprogram or for all ED grant programs.
Step 26Note: You can add optional clauses or add a unique clause in the Selected Award Clauses section.
Step 27To add an optional clause, click the Add/Remove Clauses button.
Step 28The Add/Remove Clauses page displays the list of available optional clauses.
To add an optional clause, click the appropriate checkbox to select the clause. One has been selected for you in this example.
Step 29Click the Add button to move the selected clause to the Selected Clauses list.
Step 30After you have added the appropriate clauses to the Selected Clauses list, click the Continue button to return to the Clauses tab.
Step 31The selected clause now appears on the Clauses tab.
Step 32After confirming the appropriate clauses have been added, click the Continue button to continue to the Attachments tab.
Step 33After confirming the appropriate clauses have been added, click the Continue button to continue to the Attachments tab.
Step 34Click the vertical scrollbar to scroll down.
Step 35Note: You can add optional attachments in the Optional Award Attachments section.
Step 36After confirming the appropriate attachments have been added, click the Continue button to continue to the Status tab.
Step 37The Status tab displays a history of the actions that have occurred over the life of an application/award.
Click the Continue button to continue to the Summary tab.
Step 38The Summary tab will display a summary of the information on the previous tabs.
Click the Vertical scrollbar to scroll down and review the information.
Step 39After the ensuring the information is accurate, click the Submit button to submit and save your work.
Step 40The system displays a message indicating that the changes have been saved.
You can now use the Generate Grant Award Notification (GAN) button to generate and print the GAN.
Step 41Click the Prepare link to return to the Prepare page.
Step 42Congratulations!
You have learned how to prepare a new discretionary award in G5.